Transport & Traffic

Incident Bottleneck Queue & Clearance Delay Calculator

Estimate a temporary capacity-reduction queue and cumulative delay with constant demand and two service rates.

How the calculation works

queue = (demand-reduced)*duration/60. Maximum queue at incident clearance = queue vehicles. Additional time to clear queue = queue/(normal-demand)*60 minutes. Time from incident start to queue clearance = duration+queue/(normal-demand)*60 minutes. Total vehicle delay, triangular queue area = queue*(duration+queue/(normal-demand)*60)/120 vehicle-hours.

Worked example

Example inputs — Constant arrival demand (vehicles/hour): 1800; Incident service capacity (vehicles/hour): 1200; Restored service capacity (vehicles/hour): 2400; Incident duration (minutes): 30. Expected results — Maximum queue at incident clearance: 300 vehicles; Additional time to clear queue: 30 minutes; Time from incident start to queue clearance: 60 minutes; Total vehicle delay, triangular queue area: 150 vehicle-hours.

Assumptions and limits

Deterministic point queue starts empty; constant demand and incident capacity for the specified duration, followed by immediate restoration and unchanged demand. Queue area gives total vehicle-hours of delay. Ignores spillback, changing demand, multiple incident stages, diversion, stochastic arrivals and extra free-flow travel time. This is a scenario estimate, not an operational prediction.

Reference and further reading

Read the underlying subject reference. Calculith is an independent implementation; the reference does not endorse or certify this tool.

Related calculators

Browse all 1000 calculators →

Example values are editable. Results are estimates where assumptions apply. Calculations run in your browser. Updated 2026-11-16.