Three-Stage Production Bottleneck Calculator

Compare parallel station capacities across three serial production stages.

How the calculation works

Stage A nominal capacity = 60*parallel_a/cycle_a units/hour. Stage B nominal capacity = 60*parallel_b/cycle_b units/hour. Stage C nominal capacity = 60*parallel_c/cycle_c units/hour. Line bottleneck capacity = min(60*parallel_a/cycle_a,60*parallel_b/cycle_b,60*parallel_c/cycle_c) units/hour.

Worked example

Example inputs — A cycle time per machine (minutes/unit): 1; Parallel machines at A: 1; B cycle time per machine (minutes/unit): 2; Parallel machines at B: 2; C cycle time per machine (minutes/unit): 3; Parallel machines at C: 1. Expected results — Stage A nominal capacity: 60 units/hour; Stage B nominal capacity: 60 units/hour; Stage C nominal capacity: 20 units/hour; Line bottleneck capacity: 20 units/hour.

Assumptions and limits

Scenario arithmetic using your own costs, rates and definitions. Use a common currency and matching time periods; the model does not verify accounting records or forecast future business results. Deterministic nominal capacities with perfectly shared parallel work. Blocking, starvation, changeovers, failures and quality losses reduce achieved throughput.

Reference and further reading

Read the underlying subject reference. Calculith is an independent implementation; the reference does not endorse or certify this tool.