Business & Operations
PERT Activity Duration & Uncertainty Calculator
Summarize optimistic, most likely and pessimistic activity durations using the traditional PERT approximation.
How the calculation works
PERT expected duration = (optimistic+4*likely+pessimistic)/6 days. Approximate standard deviation = (pessimistic-optimistic)/6 days. Approximate variance = ((pessimistic-optimistic)/6)**2 days².
Worked example
Example inputs — Optimistic duration (days): 2; Most likely duration (days): 5; Pessimistic duration (days): 8. Expected results — PERT expected duration: 5 days; Approximate standard deviation: 1 days; Approximate variance: 1 days².
Assumptions and limits
Scenario arithmetic using your own costs, rates and definitions. Use a common currency and matching time periods; the model does not verify accounting records or forecast future business results. Traditional weighted activity estimates, not a fitted probability distribution or complete project schedule. Correlated activities and changing critical paths are not represented.
Reference and further reading
Read the underlying subject reference. Calculith is an independent implementation; the reference does not endorse or certify this tool.
Related calculators
- Gross Margin, Markup & Unit Profit Calculator
- Product Profit, Revenue & Margin Scenario Calculator
- Break-Even, Target Profit & Margin of Safety Calculator
- Two-Product Sales Mix Break-Even Calculator
- Operating Leverage Sales Sensitivity Calculator
Example values are editable. Results are estimates where assumptions apply. Calculations run in your browser. Updated 2026-11-16.