Overall Equipment Effectiveness Calculator
Separate production availability, performance and quality to calculate OEE.
How the calculation works
Availability = (planned-stop)/planned*100 %. Performance = ideal_cycle*total/(planned-stop)*100 %. Quality = good/total*100 %. Overall equipment effectiveness = ideal_cycle*good/planned*100 %.
Worked example
Example inputs — Planned production time (minutes): 100; Stop time within planned time (minutes): 20; Ideal cycle time per part (minutes): 1; Total parts produced: 80; Good parts produced first time: 72. Expected results — Availability: 80 %; Performance: 100 %; Quality: 90 %; Overall equipment effectiveness: 72 %.
Assumptions and limits
Scenario arithmetic using your own costs, rates and definitions. Use a common currency and matching time periods; the model does not verify accounting records or forecast future business results. Use matching time boundaries and count first-pass good parts. Planned time excludes periods the process was never intended to run; OEE is not total calendar utilization.
Reference and further reading
Read the underlying subject reference. Calculith is an independent implementation; the reference does not endorse or certify this tool.
Related calculators
- Gross Margin, Markup & Unit Profit Calculator
- Product Profit, Revenue & Margin Scenario Calculator
- Break-Even, Target Profit & Margin of Safety Calculator
- Two-Product Sales Mix Break-Even Calculator
- Operating Leverage Sales Sensitivity Calculator
Example values are editable. Results are estimates where assumptions apply. Calculations run in your browser. Updated 2026-11-16.