Business & Operations

Overall Equipment Effectiveness Calculator

Separate production availability, performance and quality to calculate OEE.

How the calculation works

Availability = (planned-stop)/planned*100 %. Performance = ideal_cycle*total/(planned-stop)*100 %. Quality = good/total*100 %. Overall equipment effectiveness = ideal_cycle*good/planned*100 %.

Worked example

Example inputs — Planned production time (minutes): 100; Stop time within planned time (minutes): 20; Ideal cycle time per part (minutes): 1; Total parts produced: 80; Good parts produced first time: 72. Expected results — Availability: 80 %; Performance: 100 %; Quality: 90 %; Overall equipment effectiveness: 72 %.

Assumptions and limits

Scenario arithmetic using your own costs, rates and definitions. Use a common currency and matching time periods; the model does not verify accounting records or forecast future business results. Use matching time boundaries and count first-pass good parts. Planned time excludes periods the process was never intended to run; OEE is not total calendar utilization.

Reference and further reading

Read the underlying subject reference. Calculith is an independent implementation; the reference does not endorse or certify this tool.

Related calculators

Browse all 1000 calculators →

Example values are editable. Results are estimates where assumptions apply. Calculations run in your browser. Updated 2026-11-16.