Earned Value Project Performance Calculator
Calculate cost/schedule variances, performance indices and a constant-CPI completion-cost scenario.
How the calculation works
Cost variance = earned-actual currency. Schedule variance in value units = earned-planned currency. Cost performance index = earned/actual ratio. Schedule performance index = earned/planned ratio. EAC if current CPI persists = budget/(earned/actual) currency. ETC under same assumption = budget/(earned/actual)-actual currency.
Worked example
Example inputs — Planned value to date: 100000; Earned value to date: 80000; Actual cost to date: 100000; Approved budget at completion: 200000. Expected results — Cost variance: -20000 currency; Schedule variance in value units: -20000 currency; Cost performance index: 0.8 ratio; Schedule performance index: 0.8 ratio; EAC if current CPI persists: 250000 currency; ETC under same assumption: 150000 currency.
Assumptions and limits
Scenario arithmetic using your own costs, rates and definitions. Use a common currency and matching time periods; the model does not verify accounting records or forecast future business results. EV, PV and AC use a consistent baseline and status date. Schedule variance is expressed in budget value, not days. EAC assumes current cost efficiency persists; it is not a guaranteed forecast.
Reference and further reading
Read the underlying subject reference. Calculith is an independent implementation; the reference does not endorse or certify this tool.
Related calculators
- Gross Margin, Markup & Unit Profit Calculator
- Product Profit, Revenue & Margin Scenario Calculator
- Break-Even, Target Profit & Margin of Safety Calculator
- Two-Product Sales Mix Break-Even Calculator
- Operating Leverage Sales Sensitivity Calculator
Example values are editable. Results are estimates where assumptions apply. Calculations run in your browser. Updated 2026-11-16.